Construction Contracts in Brazil: Liability and Deadlines
When you hire someone to build something, you need to know who bears the risk for the materials, when you can reject poorly done work, and how long the contractor remains liable for the structural soundness of the construction.
The Two Types of Construction Contracts and How Risk Is Divided
Brazil’s Civil Code governs the construction contract (empreitada) in Arts. 610 to 626, and Art. 610 immediately distinguishes two types. In a labor-only contract, the contractor supplies nothing but his work. In a labor-and-materials contract, also called a mixed contract, the contractor provides the labor and also the supplies needed to carry out the contracted work.
This distinction is decisive in determining who bears the risks until delivery. Art. 611 provides that when the contractor supplies the materials, the risk of loss falls on him until the moment of delivery, unless the owner is in default for failing to accept the finished work.
In a labor-only contract, the rule is reversed. Art. 612 provides that if the contractor supplies only labor, all risks for which he is not at fault fall on the owner. The labor-only contractor answers for his own diligence, but not for the accidental loss of someone else’s materials entrusted to him.
These rules should guide how the contract is drafted from the start. Stating clearly who buys the materials, who stores them, and when the work is considered delivered prevents most of the disputes that arise when something is lost or damaged before the job is finished.
Accepting the Work and Rejecting Defective Work
Once the work is completed according to the agreement or local custom, the owner has a duty to accept it. Art. 615, however, allows the owner to refuse it when the contractor departed from the instructions received and the agreed plans, or when he disregarded the technical rules that apply to the nature of the work performed.
Rejection is not the only response to a defect. Instead of rejecting the work, Art. 616 allows the owner to accept it with a proportional reduction in the price. This is a useful solution when the defect is tolerable and rejecting the work entirely would be out of proportion to the parties’ actual interests.
Rejecting the work is not the only option: the law also allows you to accept it with a proportional reduction in the price.
When the work consists of distinct parts, or is determined by measurement, Art. 614 allows the owner to inspect it in stages, and whatever has been measured and paid for is presumed to have been inspected and approved. The contractor, in turn, is entitled to have that inspection carried out, which protects him from unfounded rejections after each stage has been delivered.
Acceptance, however, does not erase every defect. Hidden defects, which appear only with use, are governed by their own rules on the contractor’s liability, including the structural warranty in Art. 618 when they compromise the soundness or safety of the work. Accepting the work means accepting what could be inspected. It does not mean giving up claims over what was concealed.
Five-Year Liability for Soundness and Safety
The most sensitive issue in a construction contract is liability for structural quality. Art. 618 provides that, in the construction of buildings or other substantial works, a contractor who supplies both materials and labor is liable for five years for the soundness and safety of the work, both as to the materials used and as to the soil.
This five-year period is a warranty period, and the parties cannot shorten it by agreement. The rule is protective and aims at the safety of buildings and of third parties, so a contract clause that tries to cut this liability short has no effect at all.
The sole paragraph of Art. 618 addresses how the owner must react to a defect. It sets a period of one hundred eighty days, counted from the appearance of the defect, for the owner to file a lawsuit based on that provision. If the owner misses the deadline, the right it grants is forfeited. Once a soundness problem is discovered, the owner cannot put off acting indefinitely.
It helps to keep two separate things apart. The five-year warranty defines the period during which a structural defect gives rise to liability. The one hundred eighty-day period concerns bringing the specific lawsuit after the problem has come to light. Missing that second deadline does not make the defect disappear, but it takes away the owner’s use of the particular remedy provided in that article.
Setting the Price and Changing the Plans
The price also shapes the rules of a construction contract. Art. 619 provides that a contractor hired to carry out the work according to a plan accepted by the person who commissioned it cannot demand an increase in price, even if changes are introduced, unless those changes result from the owner’s written instructions. A fixed-price contract shifts the risk of ordinary cost variations to the contractor.
There is, however, a rebalancing mechanism. Art. 620 allows the price to be revised when the cost of materials or labor falls by more than one tenth of the total agreed amount, and the owner is entitled to the difference, upholding the contract’s economic balance.
Changes to the plans call for caution on both sides. When the owner imposes major changes that are out of proportion to the approved plan, Art. 625 allows the contractor to suspend the work, even if the owner is willing to bear the additional cost. This shows that a higher payment does not by itself justify any change in the contracted scope.
Suspending the Work and Other Grounds for Interruption
A construction contract can be interrupted before completion, and the Civil Code regulates the effects of that break. Art. 623 allows the owner to suspend the work at any time, provided that he pays the contractor the expenses and profits for the services already performed, plus reasonable compensation calculated on what the contractor would have earned had he finished the job.
When the contractor suspends the work without cause, the consequence is different. Art. 624 imposes on him the duty to complete the work he agreed to do, and he is liable for losses and damages if he abandons it without just cause, except in the situations where the law itself allows him to stop.
Those situations are set out in Art. 625, which allows the contractor to suspend the work because of the owner’s fault, because of force majeure, or when, during the course of the work, unforeseeable difficulties arise from geological or water-related causes that make the job excessively burdensome. Outside these cases, a work stoppage is a breach of contract.
In any of these cases, the interruption calls for a settling of accounts. Measured work, purchased materials, and documented expenses must be quantified at the moment of the stoppage. This both pays for what was performed and sizes the compensation owed, so that the dispute over how the contract ended does not pile on top of the technical dispute over the work.
Proving the Defect and Preventing Disputes Through the Contract
Once the contractor’s liability is recognized, it is up to the owner to show the defect and where it came from. Proof usually rests on a technical inspection that describes the defect, identifies its cause, and indicates whether it stems from the workmanship, the materials, or the soil. These are the elements that determine whether the warranty in Art. 618 applies.
Good contract documentation makes this showing easier. The approved plans, the descriptive specification, the written instructions exchanged between the parties, and the receipts for acceptance at each stage make it possible to compare what was contracted with what was delivered, narrowing the room for dispute over liability.
That is why prevention begins when the contract is made. Putting the scope, materials, deadlines, and acceptance conditions in writing is not excessive formality. It lets you pinpoint liability with confidence if a defect appears later, and invoke the legal remedy within the proper deadline.
A small-scale job, on the other hand, does not trigger the specific warranty in Art. 618, which is reserved for substantial construction. In those cases, the contractor’s liability for defects follows the general rules on breach of contract, which makes it even more important to spell out in the contract the expected standard of quality and the consequences of failing to meet it.
Frequently Asked Questions
Who is responsible for the loss of materials before the work is delivered?
It depends on the type of contract. In a labor-and-materials contract, Art. 611 places the risk on the contractor until delivery, unless the owner is in default for failing to accept the work. In a labor-only contract, Art. 612 places the risks on the owner, as long as the contractor was not at fault for the loss.
Can the construction warranty period be shortened by contract?
No. The five-year period in Art. 618, which covers the soundness and safety of substantial construction, cannot be reduced by agreement. A clause that tries to shorten it has no effect, because the rule protects the safety of the building and of third parties, not just the interests of the contracting parties.
Can the owner reject work that was not done as agreed?
Yes. Art. 615 allows the owner to reject the work when the contractor departed from the accepted instructions and plans. As an alternative, Art. 616 allows the owner to accept the work with a proportional price reduction, if the owner prefers to keep the result despite the defect in the workmanship.
Receba novidades por e-mail
Cadastre-se gratuitamente para receber nossos novos artigos.
Seus dados estão protegidos conforme a LGPD.
Ficou com dúvidas? Fale com um advogado especialista.
📱 Falar pelo WhatsAppAs informações deste artigo são de caráter informativo e não substituem consulta jurídica individualizada. Cada caso possui particularidades que exigem análise específica.