Decree 13.106 Creates the Federal Express Purchasing System

Decree 13.106, of August 24, 2026, regulated the Express Purchasing System and opened a platform-based path for procurement, with permanent supplier accreditation and automated ranking of offers across the federal administration.

What the decree regulates

The decree, published in the Federal Official Gazette (Diário Oficial da União) on August 25, 2026, regulates Article 79, caput, item IV, of Law 14.133/2021 in order to govern the Express Purchasing System, known by the acronym Sicx, within the federal public administration. Its immediate basis is Article 79, § 1, item VII, of the same law, which authorizes the Executive Branch to set its own rules for the auxiliary accreditation procedure used to buy common items repeatedly.

The effective date was set for September 8, 2026, so the regime is already in force. The design does not create a new type of bidding procedure. Instead, it uses accreditation as an auxiliary procedure and moves offer selection, purchase formalization, and receipt control onto a platform.

The system’s central agency is the Secretariat of Management and Innovation of the Ministry of Management and Innovation in Public Services, which exercises the powers set out in Article 19 of Law 14.133/2021. It issues supplementary rules, provides the operating platform, and drafts the accreditation notices. It may also delegate to other agencies and entities the role of accrediting body, tied to specific goods and services listed in the notice.

The decree rests on three core definitions. A public buyer is an agency or entity covered by Article 1 of Law 14.133/2021 that has been authorized by its respective government body to make purchases in the system. A private buyer includes state-owned companies, mixed-capital companies (sociedades de economia mista, state-controlled companies with private shareholders) and their subsidiaries, independent social service entities, and private nonprofit organizations. Standardized goods and services are the common items described in Article 6, item XIII, whose purchase recurs in a comparable, non-individualized way.

Permanent accreditation and the end of extra qualification requirements

For suppliers, the first practical change concerns access. Buyers join through an enrollment process set by the central agency, but supplier access stays permanently open and works through integration with the unified supplier registry. There is no application window and no opening date to watch for. Interested companies request accreditation electronically, whenever it suits them.

Accreditation notices may remain in force indefinitely and may add new standardized goods and services under the same rules. This permanence changes the commercial routine of anyone who sells to the government, because the effort shifts from one-off bidding contests to keeping the registration and the offers up to date.

One point protects accredited companies in particular. Qualification requirements are set in the notice according to the nature of the item and are proven through the unified supplier registry described in Article 87 of Law 14.133/2021. The decree expressly prohibits buyers from imposing additional qualification requirements, which removes the buying unit’s room to create local documentation demands.

An accredited supplier registers offers for the items in its product line and, for each location it serves, states prices and delivery and payment terms. It may list tiered prices based on the quantity ordered for the same item and location, and it may feed its registration through integration with platforms where it already sells the same products.

A supplier may ask to be removed from accreditation at any time, but doing so does not release it from contracts already signed. Another restriction deserves the private sector’s attention. An offer from a supplier listed in the Informational Registry of Unpaid Federal Public-Sector Credits (Cadin) is not considered eligible for public buyers, although it remains available to buyers governed by private law.

Automated ranking and the algorithm’s duty of accountability

Selecting a proposal no longer depends on a public session. It results from an automated ranking of eligible offers, following the notice’s criteria and the system’s parameters. The central agency may adjust weights and methodologies for three stated purposes: obtaining better offers, reducing market concentration, and promoting equal treatment and good governance in transactions.

The decree imposes a transparency duty on the central agency that matters directly to anyone who wants to challenge a ranking. The agency must ensure the publicity and auditability of the automated ranking models and keep technical documentation of the criteria, weights, parameters, and changes made, including the history of the ranking rules.

Publishing the ranking model and the history of the ranking rules makes the order of offers a verifiable administrative act, rather than an opaque platform result.

This documentation is the raw material for any challenge. Without a record of the weights in force on the date of the transaction, a passed-over company could not show a parameterization error or a change of criteria during the life of the offer. With it, the dispute moves out of the realm of impressions and becomes a comparison between the published rule and the result it produced.

In case of a tie, the criteria in Article 60, caput, items II to IV, and § 1, of Law 14.133/2021 apply, and if the tie persists, a drawing of lots determines the order of the offers. Selecting the top-ranked offer requires no justification. Choosing an offer that is not first in the ranking, however, requires a specific, objective justification under an act of the central agency, which creates a record that can be reviewed.

Planning, receipt deadlines, and release of payment

For public managers, the most significant change is in the paperwork. Planning is done through a preliminary technical study, which may be comprehensive, listing items from several product lines to be bought on a preferential basis up to a certain limit, or specific, tied to one or more purchases within a single product line. The comprehensive study relies on the annual procurement plan governed by Decree 10.947/2022.

The specific study is prepared directly on the platform, under Article 18, § 2, of Law 14.133/2021. The buyer is also excused from drafting terms of reference and a purchase notice, and instead selects the items and features that best meet its need, according to the central agency’s rules. The documentation required for the process is therefore considerably shorter.

The price estimate is built from the offers available on the platform, combined with the parameters in Article 23 of Law 14.133/2021 and with automated searches of the private market. To query the national database of electronic invoices, provided for in Article 23, § 1, item V, and Article 174, § 2, item VI, the system integrates with the environments of the Federal Revenue Service and the finance departments of the states and the Federal District.

The purchase unfolds through acts assigned to designated officials: selecting the offer and preparing the purchase order, confirming the selection and completing the purchase, and final acceptance. For a public buyer, the first two acts must be performed by different officials, unless purchases have been pre-authorized up to the value limit reserved in the planning stage. Completing the purchase is equivalent to contracting the item from the supplier.

The receipt deadlines are clearly defined. Provisional acceptance occurs within two business days after the delivery or service is recorded. Final acceptance occurs within ten days after provisional acceptance, unless the notice sets a different period, subject to a maximum of thirty days. An item may be rejected, in whole or in part, when it does not conform, and both rejection and partial acceptance must be justified.

The effect of silence is the part that most changes the routine of buying units. If the buyer does not respond within the deadlines above, provisional or final acceptance is deemed to have occurred automatically. Tacit final acceptance triggers a notice to the buyer, so that it can take whatever internal management steps are appropriate, and it affects the buying unit’s own reputation indicators.

Because payment to the supplier is released upon final acceptance, whether express or tacit, administrative inaction can no longer be used to delay disbursement. Whenever possible, the buyer and the supplier must be informed in advance of the estimated amounts of tax withholdings and payment splits. In case of a defect, a discrepancy, or another justified reason, the item may be returned, with pickup handled by the supplier, which the parties may agree to waive.

Integrity, sanctions, and the reputation of suppliers and buyers

The decree sets up a graduated range of responses. Minor failures, those that can be corrected, or those without significant harm allow for measures that encourage compliance, such as a warning, formal guidance, a notice to correct, or a deadline to regularize. Conduct that violates the system’s integrity, on the other hand, may lead to precautionary measures, an administrative accountability proceeding, the sanctions of Law 14.133/2021, and referral to the competent authorities.

Among the precautionary measures is temporary deactivation of accreditation, which the central agency or the buyer may apply when there are signs of irregularity, noncompliance with obligations, or risk to the performance of the offer or contract. The decree guarantees notice to the supplier and an opportunity to respond, except in urgent cases, and leaves the conditions and procedures to the central agency.

A buyer that breaches the decree’s rules or the central agency’s acts also faces consequences: its transactions may be suspended until the situation is regularized or another official is designated to act in the system. Administrative sanctions against suppliers follow Law 14.133/2021 and the notice, with the right to respond and a full defense guaranteed, and they do not extend to negotiations and contracts with entities governed by private law.

Reputation received its own treatment. Reputation mechanisms support the ranking and the improvement of purchasing, but they are purely classificatory and informational and are not equivalent to an administrative sanction. The criteria must be objective, verifiable, and nondiscriminatory, and parameters that unduly restrict competition are prohibited. Buyers are also rated, based on payment times, refusals to accept deliveries, and tacit acceptances.

Reach to other government bodies and transition rules

The system may be made available to agencies and entities of the other levels of government, to state-owned companies and mixed-capital companies and their subsidiaries, to independent social service entities, and to private nonprofit organizations. Participation respects the buyer’s legal regime and the level of government to which it belongs, with effects on planning, on the form and value of offers, on the payment regime, and on the sanctions regime.

These participants may issue operational rules and supplementary guidance governing use within their own spheres, subject to the decree and to the conditions of use set by the central agency. The platform may also integrate with public and private e-commerce environments under express conditions, including integration with the unified supplier registry and the National Public Procurement Portal.

The other integration conditions reinforce commitments already present in the procurement system: separation of duties between whoever selects the offer and whoever authorizes the purchase in the case of a public buyer, a guarantee of payment upon final acceptance, compliance with the National Public Procurement Strategy for Sustainable Development established by Decree 12.771/2025, application of Articles 42 to 49 of Complementary Law 123/2006 and of Article 26 of Law 14.133/2021, as regulated by Decree 11.890/2024, as well as transparency and traceability.

The transition regime addresses features that are not yet available. Until integration with the unified supplier registry is in place, suppliers must keep their data up to date in the Unified Supplier Registration System, and the buying agency must verify the documentation required by the notice until automatic checking is released.

Likewise, until the platform’s price estimate is operating, the buyer must check the offers available for the same item outside the system, taking into account the administrative cost of a process run off-platform. And until the value-limit reservation and automatic payment release are available, disbursement follows the ordinary procedure for executing public spending, within a maximum of thirty days from receipt.

The decree also amended Decree 11.878/2024, which now expressly addresses accreditation under items I to III of Article 79 of Law 14.133/2021, leaving item IV to the new regime. The Secretariat of Management and Innovation remains authorized to issue the supplementary rules and guidance needed for implementation.

Frequently Asked Questions

Does a company have to wait for a notice to open before selling through this system?

No. Supplier access stays permanently open and works through integration with the unified supplier registry, with accreditation requested electronically. Accreditation notices may remain in force indefinitely and may add new standardized items subject to the same rules, so entry does not depend on an application window.

Can a public buyer require qualification documents that are not in the notice?

No. The requirements are set in the notice according to the nature of the item and are proven through the unified supplier registry under Article 87 of Law 14.133/2021. The decree prohibits buyers from imposing additional qualification requirements. During the transition, the buying agency may only verify the documentation already required by the notice, until the platform’s automatic checking becomes available.

What happens if the buying unit does not respond about a delivery?

Silence has legal effect. Failing to respond within two business days after the delivery is recorded results in tacit provisional acceptance, and failing to respond within ten days after provisional acceptance results in tacit final acceptance, subject to the thirty-day limit. Because payment is released upon final acceptance, the buyer’s inaction does not delay disbursement and also affects the unit’s reputation indicators.